In this form of agreement, the contractor agrees to perform the work for an agreed fixed price. Exceptions to that fixed price include costs of Owner Selected Items (OSI) in excess of the agreed OSI allowance, and the cost of work performed beyond the extent of the original scope.  The value of these exceptions would be added to the initial fixed price via Change Order.